
Construction in progress at Gorgas playground on the 2500 block of Jefferson Street
Harrisburg is on track to finish several major park upgrades in the coming weeks, but is up against the clock to complete renovations before grant funds expire.
In October 2022, the city was awarded a $13 million reimbursement grant by the Pennsylvania Department of Community and Economic Development (DCED) for improvements at Reservoir, Wilson, 7th & Radnor and Gorgas parks, with a deadline to spend the funds in the coming months.
Three of the parks, Wilson, off of Rumson Drive in Allison Hill, 7th & Radnor sports field in Uptown and Gorgas playground, adjacent to the sports field, seem to be on track for a December completion date. However, work to construct a “spray alley” at Reservoir Park in Allison Hill appears to have just started, as fencing was only recently installed around the construction site in the park.
According to the city’s contract with DCED for the grant money that’s funding all four park upgrades, all $13 million needs to be spent by Jan. 31, 2026 in order for Harrisburg to receive the full amount.
However, as of Nov. 14, Harrisburg had only submitted one invoice to DCED for $2,500, which is being processed, according to DCED.
The $13 million came from the state’s Community Development Block Grant-CARES Act (CDBG-CV) funding, money the state received from the federal government to address COVID.
Harrisburg Director of Communications Mischelle Moyer said that Wilson, 7th & Radnor and Gorgas parks are currently under construction and slated to be completed by the end of the year. When visiting the construction site at 7th & Radnor park and Gorgas playground, construction workers told TheBurg that they would likely be done in early December.

New basketball courts and pavilion at 7th & Radnor sports park
Plans for 7th & Radnor included a complete overhaul. New basketball courts, a new pavilion, a dugout, a walking path and other features were already constructed. The contractors on site said that the park is about 80% complete, with mostly paving, concrete and electrical work yet to be done. Much of that is weather-dependent as winter months approach.
At Gorgas, new playground equipment has been installed. Paving work is still needed, as well as installing a rubber surface around the equipment and electrical work.
Contractors also estimated that Wilson was at about the same stage. Planned upgrades there include playground equipment, restrooms and pavilions as well, although none were visible on-site as of this week.
Parks and Recreation Director Sasha Ross previously told TheBurg that work at Reservoir Park would begin this past Monday and said that she was confident it would be completed by the grant deadline. When visiting the park on Thursday, fencing blocked off a large section, including grass and parking lot space and construction machinery was on site, although no construction work was visible at the time.
Plans for Reservoir Park include constructing a spray alley with water features, among other updates.

Fencing has gone up at Reservoir Park
According to DCED, the budget for each park is as follows:
- 7th and Radnor Park and Gorgas, $6,122,000
- Reservoir Park – Spray Park Alley, $3,601,116
- Wilson Playground, $3,001,116
- Project administration, $281,499
According to the contract, the city must incur all of the funds by the end of the contract or unspent funds will be revoked. The contract states that the city has 30 days after the deadline to submit invoices. Moyer did not respond to questions about how much money has been spent so far.
DCED said that the city may reallocate funds among the approved CDBG-CV activities if requested and approved by DCED.
A DCED spokesperson confirmed that Harrisburg requested a 30-day extension from its previous Dec. 29, 2025 deadline. This is the third extension that Harrisburg has received for the grant, which originally would have expired at the end of 2023.
At a November 2024 City Council meeting, when discussing the grant money, city Solicitor Neil Grover stated that DCED had “insisted” that they could not change the Dec. 31, 2025 deadline to spend the money. However, they now have an additional 30 days.
DCED officials said that Harrisburg explained extension requests as due to “delays by COVID-related scarcity of design/engineering contractors and supply chain constraints,” as well as “the complexity of the parks project that extended the environmental review, design/engineering, and contracting for economies of scale aspects of the project.”

Construction in progress at Wilson Park
When initially awarded the money, the city had a fifth project that they were set to receive money for: improvements to Jackson Lick pool. However, the city in 2024 reallocated the $5 million that would’ve gone to the pool to the other four parks, saying that, because of legal issues with the pool, the project would not be able to be completed by the grant deadline. Harrisburg was facing legal negotiations around the pool’s ownership with the Harrisburg School District, which owns the property.
According to DCED, out of the grant awardees announced in October 2022, all have completed their projects except for Harrisburg and Tioga County – both of which are underway. Harrisburg received the largest grant award of all other projects awarded in the same funding round.
If you like what we do, please support our work. Become a Friend of TheBurg!